This project consists of flooring system upgrades for 8th & Market, 9/10th & Locust, 12/13th & Locust and 15/16th & Locust Street Stations concourses.
The work is scheduled to be completed in phases and includes the preparation of the existing epoxy floors to receive a new finish, repairs to floor cracks and the installation of a new finish with non-skid additive.
Construction schedule:
Subject to change
- Phase 1: Completed
- Phase 2: Completed
- Phase 3: Completed
- Phase 4: 7 p.m. Friday, 10/11 to 5 a.m. on Monday, 10/14
- OPEN: 8th & Market North
- CLOSED: 8th & Market South
- Phase 5: 7 p.m. Friday, 10/18 to 5 a.m. on Monday, 10/21
- OPEN: 8th & Market North
- CLOSED: 8th & Market South
What to expect:
Sections of the stations will be closed and customers will notice construction walls. Access to stairwells, elevators, ticket vending machines, and fare gates may be limited and have detours in place. Customers may need to use a different stairwell to access street level. It is advised to allow extra time to access the platform.